The auditor has notes for the auditor.
GAO's Inspector General found that GAO changed its $1 million IT modernization plan without documenting why and could not easily report total initiative costs.
What happened
GAO's Office of Inspector General publicly released its IT modernization audit on August 28. GAO paid $1 million in 2021 for a five-year modernization plan whose initiatives were projected to cost about $29 million. Less than 18 months after the plan was finalized, GAO moved to an ongoing modernization strategy without documenting the rationale, leaving current leaders unaware of the decision-making process.
GAO reported 39 of 61 modernization initiatives complete as of May 2026. It tracked modernization costs, but some smaller initiatives sat under larger projects in the cost system, making the actual total difficult to determine. GAO agreed to improve controls for documenting significant changes and fully tracking future project costs.
Why CMCoE cares
Documentation, baselines, institutional knowledge, and cost traceability are the controls acquisition teams expect oversight bodies to demand from everyone else. When the audit institution has the same gap, the lesson is less that one office failed and more that modernization can outrun governance anywhere.
Regulatory fine print
This is an internal GAO Inspector General audit, not a GAO bid-protest holding, procurement rule, or finding that $29 million was spent or wasted. The $29 million figure was the plan's projected initiative cost. The report says most initiatives continued under the new strategy and that 39 of 61 were complete. Its recommendations apply to future documentation and cost tracking, and GAO concurred.
Sources
- GAO OIG - Information Technology Modernization (U.S. Government Accountability Office, Office of Inspector General, )